A cubic yard is 27 cubic feet. Divide that by the bag yield and you have your answer.

How many 80 lb bags of concrete are in a yard?

It takes 45 bags at 80 lb to make one cubic yard of concrete.

An 80 lb bag of standard pre-mixed concrete yields 0.60 cubic feet, and a cubic yard is 27 cubic feet: 27 ÷ 0.60 = 45. For other bag sizes it is 60 bags at 60 lb, 72 at 50 lb, and 90 at 40 lb.

At roughly $6.50 a bag that is about $293 per cubic yard against $140-190 for ready-mix delivered — so bags only make sense below about one cubic yard, once you weigh in the short-load fee a plant charges on small orders.

The short answer

45 bags at 80 lb. 60 bags at 60 lb. 72 bags at 50 lb. 90 bags at 40 lb.

Those come straight from the yields printed on the bag: an 80 lb bag of standard pre-mixed concrete makes 0.60 cubic feet, and 27 ÷ 0.60 = 45.

Concrete bag yields and bags per cubic yard
Bag sizeYield per bagBags per cubic yardBags per cubic metre
40 lb bag0.3 ft³90 bags118 bags
50 lb bag0.375 ft³72 bags94 bags
60 lb bag0.45 ft³60 bags78 bags
80 lb bag0.6 ft³45 bags59 bags
90 lb bag0.675 ft³40 bags52 bags
20 kg bag0.331 ft³82 bags107 bags
25 kg bag0.414 ft³65 bags85 bags
30 kg bag0.497 ft³54 bags71 bags

What a yard of bagged concrete actually costs

This is where the chart earns its keep, because the per-bag price hides how expensive bagged concrete is by volume:

Cost per cubic yard, bagged versus delivered
OptionUnit pricePer cubic yard
40 lb bags$4.00$360
60 lb bags$5.50$330
80 lb bags$6.50$293
Ready-mix delivered—$140-190 plus short-load fee

Bagged concrete is roughly twice the price per cubic yard of ready-mix. What keeps it competitive on small jobs is that ready-mix plants charge a short-load fee of $60-150 below about 3-5 yards and many will not deliver less than a yard at all.

The break-even lands around 1-2 cubic yards. Below a yard, bags. Above two yards, order a truck. In between, run the numbers both ways and weigh in the labour — 45 bags is four to six hours of mixing, and a slab has to be poured in one go.

Yields vary by mix type

The figures above are for standard pre-mixed concrete. Speciality mixes are denser or lighter and yield differently:

Always check the bag. Manufacturers print the yield on the front, and it is the only number that reflects what you are actually buying.

Common questions

How many 80 lb bags of concrete make a yard?

45. An 80 lb bag yields 0.60 cubic feet and a cubic yard is 27 cubic feet.

How many 60 lb bags of concrete make a yard?

60. A 60 lb bag yields 0.45 cubic feet.

How many 50 lb bags of concrete make a yard?

72 bags of standard mix at 0.375 cubic feet each. Fast-setting mix in 50 lb bags has the same yield, so also 72.

Is it cheaper to buy bags or ready-mix concrete?

Ready-mix is about half the price per cubic yard, but short-load fees of $60-150 apply under roughly 3-5 yards. Bags win below one cubic yard; ready-mix wins above two.

How much does a bag of concrete cover?

An 80 lb bag yields 0.60 cubic feet, which is 1.8 square feet at 4 inches thick. A 60 lb bag covers 1.35 square feet at 4 inches.